2.4.3 Installation of Seakeeper

  1. Locate and position four foundation spacers (P/N 11241) onto hull structure.
    1. For dissimilar metal foundations, locate and position four isolation gaskets (P/N 11145) onto foundation beams and apply a small bead of marine sealant (SILI-THANE 803 or equivalent) between both mating surfaces of each isolation gasket where it contacts the beam and the Seakeeper.
  2. Lower Seakeeper into position onto foundation beams and align over drilled holes.
  3. Install Mounting Bolts:
    1. For Blind-Hole installations (P/N 90400 – Seakeeper 6 / 5 Bolt-In Kit), install the Seakeeper supplied M12-1.75 fasteners to maintain a minimum thread engagement of 0.71 in. (18 mm). Apply a moderate coat of nickel-based anti-seize (e.g., SAF-T-EZE nickel grade anti-seize, SBT-4N or equivalent) to the threads of each bolt and include a small bead of marine grade sealant (e.g., SILI-THANE 803 or equivalent) under each bolt head and washer before installation. See Figure 11.
    2. For Through-Bolt installations (P/N 90660 – Seakeeper 6 / 5 Through-Bolt Kit), install the Seakeeper supplied M12-1.75 fasteners to maintain a minimum of 2 threads protruding past nut. Apply a moderate coat of nickel-based anti-seize (e.g., SAF-T-EZE nickel grade anti-seize, SBT-4N or equivalent) to the threads of each bolt and include a small bead of marine grade sealant (e.g., SILI-THANE 803 or equivalent) under each bolt head and washer before installation. See Figure 12.
  4. Torque all fasteners to 95 ft-lbs (129 N-m).
    1. New bolts, matching the Seakeeper specification, must be used for each installation and reinstallation that meet the requirements listed above.
  5. Proceed to electrical and cooling portion of the installation.
Figure 9 Seakeeper 6 Bolt-In Installation
Figure 10 Seakeeper 6 Stack Arrangement
Figure 11 – Blind Hole Details
Figure 12 – Thru-Bolt Details