Seakeeper 5 / 6 Installation Manual (90402-5) 6/5-233-5847 to Current

1.0 Introduction

Seakeeper 6 / 5

Installation Manual

90402, Revision 5

*THIS MANUAL ALSO COVERS THE SEAKEEPER 5 MODEL*

Applicable to model serial number 6/5-233-5847 and after.

This document is intended to give details and guidance to a boat builder or equipment installer to install the Seakeeper 5 and Seakeeper 6 Stabilization Systems.

Reference Documents


1.1 Precautions

There is a large torque about the gimbal axis when the Seakeeper is precessing. Seakeeper cover panels are provided to prevent personnel or equipment from contacting the Seakeeper while it is in operation. These covers should not be stepped on or have anything placed on top. The covers should always be in place during operation.

_____________________________________________________________________________________________________

If it is ever necessary to access the Seakeeper while the flywheel is spinning, the Seakeeper must be locked at the display to stop the Seakeeper from precessing.

_____________________________________________________________________________________________________

Stand clear of the Seakeeper and all moving components.

_____________________________________________________________________________________________________

The unit may be started remotely. Assume it could move without warning.

_____________________________________________________________________________________________________

The following must be true before accessing the Seakeeper:
* Input power must be disconnected for at least 10 minutes
* It must be locked
* Flywheel must be at zero speed


  1. Seakeeper must only be lifted from the supplied lifting eyes (see Section: Transport and Unpacking).
  2. Seakeeper flywheel is supported by precision bearings. Make certain while unpacking and lifting Seakeeper assembly to NOT drop or impart mechanical shock as damage to bearings could result.
  3. While handling / installing Seakeeper assembly, protect exposed hydraulic brake cylinder rods (See Figure 1) from scratches or damage as this could lead to premature seal failure and oil leaks.
  4. While handling / installing Seakeeper assembly, do not allow electrical fittings that exit bottom of Seakeeper enclosure to come in contact with any surface or object as this could damage the fittings and potentially affect the vacuum integrity of the enclosure.
  5. Exercise care to protect the painted finish as damage to finish could lead to early appearance degradation of installed Seakeeper.
Figure 1 Seakeeper 6

1.2 Transport & Unpacking

Reference Documents

1.2.1 Transport

  1. Use a Seakeeper provided shipping crate for transport, P/N 10977. Overall dimensions of a fully packed crate are 43.5 L x 41.5 W x 36.25 H in. (1.10 L x 1.05 W x 0.921 H m) with a weight of 1100 lbs (500 kg).
  2. Seakeeper 6/5 crates can be stacked up to two (2) units high. Only like units should be stacked, i.e., Seakeeper 6/5 on top of a Seakeeper 6/5
  3. Both Air and Ground transport are acceptable.
  4. Seakeeper shipping crates must be transported in environmental conditions between 32°F and 140°F (0°C and 60°C).

1.2.2 Unpacking Crate

  1. Reference Seakeeper Drawing No. 90389 – Seakeeper 6 Hardware Scope of Supply, for items that ship with the Seakeeper.
  2. Remove electrical components, cables, and misc. items and set aside.
  3. Remove packing materials that secure Seakeeper assembly inside the crate.
  4. Remove top and angled face cover panels to access lifting eyes.
  5. Attach spreader bar (P/N 80067) to the two lifting eyes located on the top of the Seakeeper enclosure. Stay clear of any other parts on the Seakeeper. The Seakeeper 6 weighs 870 lbs (395 kg). See Figure 2 below.
Figure 2 Seakeeper 6 Lifting Arrangement
P/N 80067 – Seakeeper 6 Low Profile Lifting Bar

2.0 Mechanical Installation

2.1 Mechanical Installation Introduction

The Seakeeper 6 is capable of producing loads up to 3820 lbs (17 kN) at each of the four mounts. These forces should be considered to be acting simultaneously, fully reversing, and will repeat an infinite number of times. Careful consideration should be given to foundation design to ensure it is capable of transferring these loads into the hull. These loads do NOT include vessel motion accelerations, such as vertical slam loads which can be significant for higher speed vessels. The responsible party for designing the supporting structure (boat builder, installer, or hired sub-contractor) must accommodate the above forces plus a reasonable factor of safety. Seakeeper recommends a minimum safety factor of 3.0 (yielding a Safety Margin of 2.0).

There are two methods of installing the Seakeeper 6:
1. Bolt-In Installation
2. Saddle Installation

It is assumed that the installer is familiar with bonding using high strength adhesives or mechanical fasteners to marine structures and has performed structural analysis to assure the structure to which the Seakeeper mounts can properly transfer the loads the Seakeeper creates into the hull structure. If the installer has any doubt about the ability of the structure to transfer the loads to the hull then a licensed naval architect or marine engineer should be contacted to do a structural analysis.

The installer should review the following list of reference drawings to ensure the installation procedure is fully understood.

Reference Documents & Drawings:

2.2 Selection of Installation Location

Seakeeper can only assess installation location regarding its impact on Seakeeper operation and serviceability. Seakeeper cannot determine how the installation location will affect the vessel static or directional stability other than cyclic roll reduction. The Installer is responsible for considering the Seakeeper‘s effect on the CG location, trim, overall stability, and performance of the vessel.


Selection of mounting location of Seakeeper should consider the following desirable features:

  1. Overhead access or sufficient clearance for removal / re-installation of the Seakeeper for overhaul in future years. Provide adequate clearance for maintenance, as shown in Figure 1 and 2 below.
  2. The Seakeeper should be installed in a dry space to minimize effects of corrosion.
  3. Installed near vessel’s longitudinal center of gravity (LCG) to minimize effects on trim and performance in various loading conditions.

VIEWS SHOWING RECOMMENDED CLEARANCES AROUND THE SEAKEEPER FOR USE OF HANDTOOLS, EASE OF MAINTENANCE, INSTALLATION, AND PROPER OPERATION.

Figure 1 Seakeeper 6 Installed Clearance Considerations

Figure 2 Seakeeper 6 Transverse Beams Clearance Considerations

Refer to Figure 2 for recommended clearances to transverse beams. If a transverse beam is located under the forward brace, it must be 4 in. (102 mm) from the edge of the saddle beams to provide the necessary clearance for the swing of the motor power cable during precession. Clearances aft of the Seakeeper are shown to provide access for maintenance.


2.2.1 Noise/Soundproofing

Seakeeper noise has been measured under steady state conditions (no wave load) in Seakeeper‘s Engineering Lab and in our Factory Demo Boat. The steady state noise is typically <72 dBC at 1 meter. As the frequencies emitting the highest sound pressures are low (like other marine machinery), it is recommended that the Seakeeper be installed in a machinery space that is already treated with soundproofing.

2.3 Selection of Installation Method

The Seakeeper 6 can be affixed to the hull structure using two methods:

1) Bolt-In installation
2) Saddle installation

See figures below.

Figure 3 Option 1- Direct Fastening of Seakeeper Foundation to Ships Structure

Option 1 would be applied when a metal structure is available for attachment. The foundation would fasten directly to hull structure using isolation gaskets and sixteen M12-1.75 fasteners. Depending on the structure to which the Seakeeper is fastened, blind threaded holes or thru-bolting can be utilized.

Figure 4 Option 2- Saddle Installation (4 Places)

Option 2 would be most commonly used on a hull constructed of glass reinforced plastic (GRP) or fiberglass. For this option, four 7.5 in. (191 mm) long by 3.38 in. (85.7 mm) deep saddles are bonded to properly spaced and prepared structural members that are an integral part of the hull structure. Seakeeper recommends using a structural adhesive with a lap shear strength of 2000 psi (13.8 MPa) or greater. Careful consideration should be exercised by the installer while selecting the appropriate adhesive. Compatibility with the Seakeeper’s cast aluminum A356- T6 saddles, hull structure and pot life are three important factors to consider. Proper surface preparation in accordance with adhesive manufacturer’s recommendations prior to installation is very important.

2.4 Bolt-In Installation

2.4.1 Preparation of Vessel Structure

Seakeeper provided mounting hardware is intended to apply to typical installation arrangements. However, each installation, especially custom aftermarket foundations, should be thoroughly reviewed to ensure the provided hardware meets the required thread engagement for the Seakeeper unit being installed. The mounting bolt thread engagement requirements are outlined in the Installation Manuals and Installation Details Drawings for each Seakeeper model. This also applies to Seakeeper model adapter kits and OEM built frames where the bolt hole depth should be checked to ensure the bolts will not bottom, preventing the bolts from achieving the intended preload.

The Seakeeper supporting structure should be parallel to the vessel waterline, with up to 2 degrees allowance for trim.

In addition, the four areas on top of the beams on which the feet of the Seakeeper foundation and isolation gaskets will rest need to be co-planar within .06 in. (1.5 mm) to minimize potential distortion of Seakeeper support frame when installed. The isolation gaskets are only used when the Seakeeper 6 is mounted to a dissimilar metal structure.

When the Seakeeper provided hardware is not appropriate, the bolt specification (diameter and thread pitch) and grade should be matched in the required length and used with the Seakeeper provided washers. Mounting bolts should always be torqued to the Seakeeper specification. All Seakeeper provided bolts are metric course thread. Hardware specifications are also listed in the Installation Manuals and Installation Details Drawings.

Refer to Seakeeper Drawing No. 90398 – Seakeeper 5/6 Bolt-In Installation Details. Important dimensional and load information is given in this drawing that will impact the design details of the structure that will receive the Seakeeper. It is assumed that a proper structural analysis has been performed for the hull structure to which the Seakeeper will be fastened to ensure proper strength margins for the loads the Seakeeper will create during operation.

Seakeeper provides an installation template kit, P/N 90392, which contains four plates that mimic the mating surfaces of the four feet located on the Seakeeper’s foundation. These plates have 4 holes located at the same centers as the mounting holes on the Seakeeper. The fixture locates the hole patterns at the proper spacing both in the forward-aft direction and the port-starboard direction. See Figure 5 below. Once assembled, the fixture can be used to check clearances and alignment of the hull structure.

Note: Do NOT use the installation fixture to establish Seakeeper envelope dimensions. Refer to Drawing No. 90398 – Seakeeper 6 Bolt-In Installation Details, for envelope dimensions. A 3-D model of the Seakeeper is available on the Seakeeper website (www.seakeeper.com) to aid in designing the Seakeeper foundation and the space around the Seakeeper.

NOTE: MAKE SURE NO OBSTRUCTIONS FROM THE HULL STRUCTURE CAN BE SEEN WITHIN THE INSIDE OF THE INSTALLATION TEMPLATE KIT (INSIDE THE MARKED RED LINES). REFERENCE SEAKEEPER DRAWING NO. 90398 – SEAKEEPER 6 BOLT-IN INSTALLATION DETAILS.

Figure 5 Installation Template Kit, P/N 90392
Figure 6 Seakeeper 6 Bolt-In Clearance Dimensions

CAUTION: Tight clearances from cable guide bands and brake side gimbal shaft to hull structure. See below for brake side gimbal shaft clearance. See above figure for dimensions and reference Seakeeper Drawing No. 90398 – Seakeeper 6 Bolt-In Installation Details, for complete Seakeeper envelope.

Figure 7 Brake Side Gimbal Shaft Clearance

2.4.2 Transfer of Holes to Boat Structure

  1. Lower assembled fixture onto hull structure.
  2. The four areas where the feet of the Seakeeper will rest should be coplanar to within .06 in. (1.5 mm). See figure below.
  3. Align fixture in desired location and transfer holes from fixture plate to the foundation structure. Note that holes in fixture plate are ø0.487 in. (12 mm). A transfer punch is supplied with installation template kit, P/N 90392.

Figure 8 Bolt-In Hole Transfer Fixture

2.4.2.1 Blind Hole Installation

  1. Remove Template Fixture and drill sixteen(16) 0.49 in. (12.5 mm) holes perpendicular to the vessel structure to a minimum depth of 0.94 in. (24 mm). Take special care to drill perpendicular to mounting surface. A drill guide is recommended. Remove any impeding obstructions.
  2. Tap drilled holes for helical thread inserts per documentation accompanying helical threaded inserts.
  3. Install sixteen (16) M12-1.75 X 18 mm threaded inserts into holes in hull structure at drilled and tapped locations using threaded insert manufacturer provided installation tool.
  4. Remove threaded insert prong / tang after threaded inserts are installed.
Example threaded insert
M12-1.75 X 18 mm

2.4.2.2 Through-Bolt Installation

  1. Remove Template Fixture and drill sixteen (16) 0.512 in. (13 mm) ø holes perpendicular to the vessel structure. Take special care to drill perpendicular to mounting surface. A drill guide is recommended.

2.4.3 Installation of Seakeeper

  1. Locate and position four foundation spacers (P/N 11241) onto hull structure.
    1. For dissimilar metal foundations, locate and position four isolation gaskets (P/N 11145) onto foundation beams and apply a small bead of marine sealant (SILI-THANE 803 or equivalent) between both mating surfaces of each isolation gasket where it contacts the beam and the Seakeeper.
  2. Lower Seakeeper into position onto foundation beams and align over drilled holes.
  3. Install Mounting Bolts:
    1. For Blind-Hole installations (P/N 90400 – Seakeeper 6 / 5 Bolt-In Kit), install the Seakeeper supplied M12-1.75 fasteners to maintain a minimum thread engagement of 0.71 in. (18 mm). Apply a moderate coat of nickel-based anti-seize (e.g., SAF-T-EZE nickel grade anti-seize, SBT-4N or equivalent) to the threads of each bolt and include a small bead of marine grade sealant (e.g., SILI-THANE 803 or equivalent) under each bolt head and washer before installation. See Figure 11.
    2. For Through-Bolt installations (P/N 90660 – Seakeeper 6 / 5 Through-Bolt Kit), install the Seakeeper supplied M12-1.75 fasteners to maintain a minimum of 2 threads protruding past nut. Apply a moderate coat of nickel-based anti-seize (e.g., SAF-T-EZE nickel grade anti-seize, SBT-4N or equivalent) to the threads of each bolt and include a small bead of marine grade sealant (e.g., SILI-THANE 803 or equivalent) under each bolt head and washer before installation. See Figure 12.
  4. Torque all fasteners to 95 ft-lbs (129 N-m).
    1. New bolts, matching the Seakeeper specification, must be used for each installation and reinstallation that meet the requirements listed above.
  5. Proceed to electrical and cooling portion of the installation.
Figure 9 Seakeeper 6 Bolt-In Installation
Figure 10 Seakeeper 6 Stack Arrangement
Figure 11 – Blind Hole Details
Figure 12 – Thru-Bolt Details

2.5 Saddle Installation

2.5.1 Saddle Installation Introduction

Seakeeper recommended adhesives are listed in TB-90382 – Structural Adhesives Recommendations. Seakeeper recommends using a structural adhesive with a lap shear strength of 2000 psi (13.8 MPa) or greater. Careful consideration should be exercised by the installer when selecting the appropriate adhesive, such as working time, material compatibility, and surface preparation are three important factors to consider. Proper surface preparation in accordance with the adhesive manufacturer’s recommendations prior to installation is critically important. Information regarding pot-life, structural properties and material compatibility can be found on the adhesive product’s technical data sheet (TDS). An etching/cleaning primer compatible with the adhesive should be used on all aluminum surfaces if recommended by the manufacturer. Typically, two-part methacrylate based adhesives are the best options for bond-in installations such as Plexus MA590 and Sci-Grip SG300, which provide compatibility with aluminum and FRP substrates, adequate working time, and exceed the strength requirements. See Sheet 5 of Seakeeper Drawing No. 90399 – Seakeeper 5/6 Bond-In Installation Details, for loads information and recommended adhesive properties.

2.5.2 Preparation of Hull Structure

Refer to Seakeeper Drawing No. 90399 – Seakeeper 5/6 Bond-In Installation Details. Important dimensional and load information is given in this drawing that will impact the design details of the structure that will receive the Seakeeper as well as selection of the adhesive to bond the Seakeeper into the hull.

The foundation “saddles” of the Seakeeper are designed to be bonded directly to the composite hull structure of the vessel to effectively distribute gyroscopic loads. Complete coverage of the saddles and the hull structure surfaces is required for bond-in installations. Seakeeper recommends having a minimum of 1.6 L / 0.41 gal of adhesive, on hand for installation. Number of cartridges required is determined by dividing total volume by cartridge volume. Some adhesives require etching primer for aluminum surfaces (Plexus MA590 requires PC120 primer). Both manual and pneumatic application guns are available from adhesive manufacturers. Two workers should apply the adhesive at the same time to finish the installation before the adhesive starts to cure. To aid in determining the quantity of adhesive required, the interior surface area (bonding surfaces) of each saddle is 58.2 in.2 (375 cm2) for a total bonded surface area for all four saddles of 232.5 in.2 (1500 cm2).

The hull structure supporting the Seakeeper should be installed so the Seakeeper is parallel to the waterline. The four areas on top of the beams that the saddles will bond to need to be co-planar within .13 in. (3 mm) for consistent adhesive bond gap. In addition, the four areas on top of the saddles on which the feet of the Seakeeper foundation will rest need to be co-planar within .06 in. (1.5 mm) to minimize potential distortion of Seakeeper support frame when installed.

Note that any paint or gel-coat present in bond area should be removed so that adhesive will bond directly to laminate fibers and resin. Fiberglass and aluminum surfaces should be sanded in a cross-hatch pattern with 80 grit sandpaper and thoroughly cleaned prior to adhesive application.

Seakeeper provides an installation fixture template, P/N 90392, that locates the saddles at the proper spacing both in the forward-aft direction and the port-starboard direction. See Figures 13 & 14 below. Once assembled with the provided saddle fittings, the fixture can be used to check saddle clearances and alignment of the hull structure. The fixture will allow the builder / installer to lay-up and adjust the foundation dimensions to create a low-clearance fit between the Seakeeper foundation saddles and the hull structure. Shear strength of the adhesive will be maximized if the cured thickness between the vessel structure and Seakeeper saddles is at the thinner end of the adhesive manufacturer’s recommended range. Therefore, the fixture should be used to confirm that the overall dimensions of the foundations are square and level and that the adhesive gap is within Seakeeper’s maximum recommended thickness of .13 in. or 3 mm.

Note: Do NOT use the installation fixture to establish Seakeeper envelope dimensions. Refer to Drawing No. 90399 – Seakeeper 5/6 Bond-In Installation Details, for envelope dimensions. A 3-D model of the Seakeeper is available on the Seakeeper website (www.seakeeper.com) to aid in designing the Seakeeper foundation and the space around the Seakeeper.

NOTE: MAKE SURE NO OBSTRUCTIONS FROM THE HULL STRUCTURE CAN BE SEEN WITHIN THE INSIDE OF THE INSTALLATION TEMPLATE KIT (INSIDE THE MARKED RED LINES). SEE DRAWING NO. 90399 – SEAKEEPER 5/6 BOND-IN INSTALLATION DETAILS.

Figure 13 Exploded View of Saddle Installation Fixture
Figure 14 Saddle Installation Fixture on Notional Hull Structure

2.5.3 Fiberglass Hull Preparation

  1. Position installation fixture (Figure 15) on hull girders noting recommended clearances for maintenance from Figure 2 (in Section: Selection of Installation Location). Check that the screws fastening the saddles to the installation fixture are tight (Figure 13).
Figure 15 Installing Fixture on Hull
  1. Mask hull area (Figure 16) around foundation saddles for easy clean-up and to create outline of surface area to receive adhesive (Figure 15). Ensure that the bond gap is within Seakeeper’s recommended thickness, or 3 mm if using Plexus MA590 or Sci-Grip SG300.
Figure 16 Masking Perimeter of Saddles
  1. Raise fixture clear of foundation. Check all four mounting areas are co-planar to within .06 in. (1.5 mm) to each other, as well as parallel to the water line plane, as shown in Figure 17.
Figure 17 Coplanar Properties of Foundation
  1. Thoroughly clean with alcohol or acetone all areas of girders to be bonded to remove any contaminates. Use new paper towels for cleaning, not shop rags.
  2. Remove any paint or gel-coat from bond surfaces so that adhesive will bond directly to laminate fibers and resin as shown in Figure 13.
  3. Thoroughly sand girder bond surfaces with 80 grit sandpaper in a cross-hatch pattern. (IMPORTANT – BOND STRENGTH MAY BE REDUCED IF THIS STEP IS SKIPPED.)
  4. Wipe surfaces clean from dust with alcohol or acetone using new paper towels, not shop rags.
  5. Re-position installation fixture on girders and double-check that the adhesive gap is within the adhesive manufacturer’s maximum recommended thickness. Seakeeper recommends a maximum gap of 3 mm if using Plexus MA590 or Sci-Grip SG300.

Note: If bonding saddles to a metal structure, follow adhesive manufacturer instructions for metal substrates.

2.5.4 Seakeeper Saddle Preparation

  1. Ensure that screws fastening saddles to the installation fixture are tight (Figure 13).
  2. Check that each saddle contains 2 plastic screws which will ensure an adhesive gap of .080 in. (2 mm) on top surface of hull as shown in Figure 18.
Figure 18 Saddle Cleaning

3. Thoroughly sand all saddle inside surfaces with 80 grit sandpaper. (IMPORTANT – BOND STRENGTH MAY
BE REDUCED IF THIS STEP IS SKIPPED.)

4. Wipe surfaces clean from dust with alcohol or acetone using new paper towels, not shop rags.

5. If using Plexus MA590 adhesive, apply Plexus PC-120 surface conditioner to inside surfaces of Seakeeper
foundation saddles in accordance with manufacturer instructions. These instructions are located at the end
of this section. If using an alternate adhesive, check with manufacturer if any surface conditioner/etch is
required for the aluminum saddles.

2.5.5 Bonding Saddles to Hull

Note: If using Plexus MA590 adhesive, the Seakeeper saddles should be installed when PC-120 is confirmed dry.

  1. Assemble Plexus cartridge into either the manual or pneumatic gun as shown. Remove cap on cartridge and attach mixing tip. For pneumatic gun, start with low air pressure and increase until desired flow rate is achieved.
  1. Cut tip of mixing wand as shown in photo below.
  1. Prepare a second mixing wand as shown in photo below by attaching the simple flexible nozzle to the end of the mixing tip. Set aside for now as this will be used to inject adhesive into the sides of each saddle after the fixture / saddles are in position.
  1. Install provided rubber plugs in six holes of each saddle. The plugs will limit the adhesive being forced out of the injection holes in step 6 below.
  1. Apply large bead of Plexus adhesive to the hull structure as shown in the image below. Apply approximately 1/3 to 1/2 of a cartridge (150 – 200 mL) at each of the four locations. Work deliberate and fast as it takes some time to apply the adhesive to the structure. MA590 has a 90-minute working time at room temperature (73°F / 23°C). This working time can reduce to 40-50 minutes at elevated temperatures. Two workers should apply the adhesive at the same time to finish the installation before the adhesive starts to cure.
  1. Lower fixture and saddles over the hull structure and apply light downward pressure to each of the four saddles until the two nylon screws rest on the hull structure (see Figure 12). The adhesive will be forced towards the forward and aft ends of each saddle and partially down the sides of the foundation beams.
  2. Insert full adhesive cartridge along with mixing wand / nozzle assembled in Step 3 above into gun.
  3. Begin to inject adhesive into the six holes provided on each side of each of the four saddles. Follow the numbered sequence shown until the adhesive pushes out the edges of the saddle perimeter. The intent is to pump in the adhesive working from the top down and from the middle to the ends to fill the gaps and displace any air.

A complete bond is required – excess adhesive will be needed to make sure all bond gaps are filled.

  1. Repeat above steps on both sides of all four saddles.
  2. When gaps have been completely filled, clean off excess adhesive, remove plugs, and remove masking tape.
  3. Allow adhesive to cure per manufacturer’s recommendations. Follow adhesive guidelines for curing time versus temperature prior to removing the fixture.
  4. Bonding of Seakeeper saddles onto the hull is now complete. Remove installation fixture.

2.5.6 Installation of Seakeeper

  1. The four areas where the feet of the Seakeeper will rest should be coplanar to within .06 in. (1.5 mm). See figure below.

    NOTE: DO NOT INSTALL SEAKEEPER WITH 1/2 IN. SPACERS WITH SADDLE KIT.
  2. Rig Seakeeper for lifting and lower into position onto top surface of four saddles.
  3. Apply a small bead (approximately 4 mm wide) of sealant or caulk to the mating surfaces between the saddles and the Seakeeper foundation. Adjust position of Seakeeper until alignment is achieved for the 16 fasteners that will attach Seakeeper foundation frame to saddles.
  4. Install Seakeeper supplied M12-1.75 X 65 mm fasteners – apply a moderate coat of removable thread locker to the threads of each bolt and include a small bead of sealant under each washer before installation.
  5. Torque all fasteners to 65 ft-lbs (88 N-m).
  6. Proceed to electrical and cooling portion of the installation.

3.0 Electrical Installation

3.1 Electrical Installation Introduction

This section for electrical installation explains how to mount the electrical equipment and how to connect the electrical cables.

Reference Documents & Drawings:


12 VDC Power Connector,
16.4 ft (5 m), P/N 20248
M12 D-Code Ethernet Cable
82 ft (25 m), P/N 30355
ConnectBox
NMEA CAN Cable,
19.7 ft (6 m), P/N 30332
DC Seawater Pump Power Out,
16.4 ft (5 m), P/N 20334
DC Seawater Pump Power In,
16.4 ft (5 m), P/N 30327

Figure 1 Electrical Equipment for Seakeeper 6

3.2 Electrical Equipment Power Connections

AC Input Power Source Requirements

  1. Either of two AC input voltages are acceptable:
    1. 110 – 120 VAC (nominal) (+/- 10%), 1 Phase, 50/60 Hz, 30 A
    2. 208 – 230 VAC (nominal) (+/- 10%), 1 Phase, 50/60 Hz, 20 A
  2. A separate circuit breaker should be used for each Seakeeper Drive Box in multiple Seakeeper installations.

Drive Box AC Power Input Connection Instructions

  1. Cable: 3 x 10 AWG (3 x 6mm2 CSA), 10 ft (3 m) length, Seakeeper supplied pre-installed.
    1. Locate AC Power Input Cable to the Drive Box at the outward of two cable glands per figure below.
    2. Connect AC wires to a 230 V, 20 A (or 110 V, 30 A), double-pole Circuit Breaker at an AC power distribution panel.

Figure 2 Drive Box AC Power Input & Output Cable Glands

    Low Current 12 V Power Input

    1. One 12 VDC, 15 A (Customer supplied) for Seakeeper Control Power, AND
    2. One 12 VDC, 15 A OR 24 VDC, 10 A (Customer supplied) for DC Seawater Pump.
    3. A dedicated breaker should be used for Seakeeper control and Seawater Pump power for each Seakeeper unit.

    Seakeeper DC Power Connection Instructions


    Reversing polarity on the DC power input to the Seakeeper can result in damaging the electronics in the control system.

    1. 12 VDC, 15 A, 2 x 12 AWG (3 x 4 mm2 CSA) customer supplied.
      1. Install Seakeeper provided DC Power Input Cable, P/N 20248 (shown in Drawing No.90396):
        1. Route DC Power Input Cable to DC Power Distribution Panel.
        2. Terminate positive (B+, Red) conductor through dedicated over-current protection device (customer supplied) and a dedicated Seakeeper isolation switch (customer supplied) then directly to battery plus terminal.
        3. Terminate negative (B-, Black) conductor directly to battery negative terminal or negative bus.
      2. Before connecting DC Power Input Cable to Seakeeper, check for proper voltage and polarity with a DC multimeter using Figure 3 below.
      3. Connect DC Power Input Cable to 12 VDC input receptacle on Seakeeper.
    Figure 3 DC Power Input Connector Contact Assignments (front)

    When energizing DC power the first time, if Display does not power up immediately then disconnect and inspect connector polarity.


    DC Seawater Pump 12 VDC Power Input Connection Instructions

    Connecting the DC Seawater pump in any other manner than recommended by Seakeeper may cause internal failure.

    1. Install DC SW Pump Input Power Cable (P/N: 30327) to Seakeeper 6 “SW Pump DC In” (shown in Drawing No. 90396) with overcurrent protection corresponding to seawater pump selected.
    2. Connect the 16 AWG positive conductor (red) through dedicated overcurrent protection device (customer-supplied), maximum of 15 A, to dedicated battery isolation switch.
      • 24 VDC, 10 A max can be used for Seawater Pump power.
    3. Connect the 16 AWG negative conductor (black) directly to battery negative terminal or DC main negative bus bar.
    4. Before connecting DC SW Pump Input Power Cable to Seakeeper, check for proper voltage and polarity with a DC multimeter using Figure 4 below.
    Figure 412 VDC Seawater Pump Power Input
    1. Connect DC SW Pump Power Input Cable to Seawater Pump 12 VDC In connector on the Seakeeper, DEUTSCH DT04-2P connector.

    DC Seawater Pump 12 VDC Power Output Connection Instructions

    1. Connect DC SW Pump Power Output Cable (P/N 20334) to the Seakeeper 6 “SW Pump 12VDC Out” for DC power output to the seawater pump.
      1. Seawater Pump Output Power Cable is a 2 x 16AWG cable, 16 ft (5 m) length, with a size 16 female Deutsch plug.
    2. Pumps rated at 12 VDC, 15 A maximum (24 VDC, 10 A), customer-supplied, must be configured with a Deutsch DT series, 2-pin receptacle to mate with the connector shown in Figure 5.
    Figure 5 Seawater Pump Deutsch Connector
    1. The DC SW Pump Power Output Cable must be routed and installed in the vessel from the Seakeeper 6 “SW Pump 12VDC Out” Deutsch connector (pins end) to the DC seawater pump cable Deutsch connector (socket end).
    2. Connect DC SW Pump Power Output Cable plug end (socket end) to the customer-supplied receptacle end (pins end). The recommended wiring is shown in Figure 6.
    3. Contact Seakeeper if desired to install customer-supplied relay on DC SW Pump Power Output Cable to power Seawater Pump.
    Figure 6 DC SW Pump Power Output Cable

    3.3 Electrical Equipment Ground Connections

    Seakeeper to Vessel Ground Connection Instructions

    1. Connect the Seakeeper foundation ground to vessel ground as shown in Figure 7.
    2. Install Ground Cable (4 AWG or 22.0 mm2, Customer supplied) from the M6 brass ground stud on the Seakeeper rear brace to a suitable vessel ground.
      • EN/IEC 90204-1 Clauses 6.3.3 and 8.2.3
      • ABYC E-11 July 2018 Clauses 11.5.2 and 11.16.1.

    NOTE: USE ONLY THIS LOCATION FOR GROUNDING THE SEAKEEPER TO THE VESSEL GROUND.

    Figure 7 Seakeeper Ground Stud on Rear of Foundation
    1. Ground connection should be made with vessel bonding system, if available. However, the ground is not referring specifically to a bonding system but for outboard boats generally refers to the outboard engine negative terminal. Per ABYC E-11 (2018), Clause 11.5.2.7.4: If the negative side of the DC system is to be connected to the ground, the connection shall be made only from the engine negative terminal, or its bus, to the DC grounding bus. This connection shall be used only as a means of maintaining the negative side of the circuit at ground potential and is not to carry current under normal operating conditions.
    2. A proper ground connection is critically important for corrosion protection and helps to ensure the ignition protection of the unit by ensuring it does not carry any stray current.
    ABYC E-11, figure 4A

    3.4 ConnectBox Display Connections

    Seakeeper 6 / 5 Display Options

    A display is required with the installation of a Seakeeper 6 / 5 to support the full functionality of the unit through the Seakeeper App in addition to the ConnectBox. The Seakeeper App provides an interface for controlling the Seakeeper or viewing the Settings, Service, Info, and Alarm pages. The Seakeeper ConnectBox can be helm-mounted to provide an additional interface for the control of the Seakeeper but does not replace the need for a Seakeeper compatible display.

    The Seakeeper 6 or 5 has several options for establishing a Seakeeper display interface to support the Seakeeper App:

    1. Preferably, connect the Seakeeper to a compatible Multifunction Display (MFD).
    2. Install an optional Seakeeper 5″ Touch Display (P/N 90467).
    3. A combination of a compatible MFD and an optional 5″ Touch Display is also available.

    The following figure provides a schematic of the preferred display option. The subsequent sections outline the instructions and references for connecting the Seakeeper 6 in each of these display options.

    ConnectBox Connected to Compatible MFD

    Connecting to a Compatible MFD

    1. The Seakeeper 6 can be connected to a variety of available MFD systems. Refer to the Technical Bulletins Section of the Seakeeper Technical Library for manufacturer specific MFD compatibility technical bulletins.
      • MFD specific Technical Bulletins will be updated regularly as new MFD systems become compatible. Currently GARMIN, RAYMARINE, NAVICO (Simrad, Lowrance, B&G), and FURUNO offer compatible MFD models.
      • Once a compatible MFD has been selected, refer to the appropriate manufacturer specific Technical Bulletin for integration instructions.
    2. Connect Seakeeper-supplied M12 D-Code, 32.8 ft (10 m), cable (P/N 30330) to MFD manufacturer-specific Ethernet adapter cable. Custom Ethernet cables for specific MFD manufacturers are available through Seakeeper and must be purchased with the Seakeeper 6 if connecting to an MFD.

    Connecting to an Optional Seakeeper 5″ Touch Display

    If not utilizing a compatible MFD display, a Seakeeper 5” Touch Display must be purchased from Seakeeper. The Seakeeper 5” Touch Display (P/N 90467) includes the components shown in the following figure and will be integrated with the ConnectBox.

    Seakeeper 5″ Touch Display Components
    P/N 90467
    1. Determine location of Seakeeper 5” Touch Display:
      1. The desired location of the 5” Touch Display must be determined with respect to the vessel’s arrangement.
      2. The 5” Touch Display should be located on or near the helm or another easily accessible location.
    2. Route CAN communications cable:
      1. The CAN Cable, (labelled NMEA 2000 Cable in figure above), is a 32 ft (10 m) shielded cable that connects the ConnectBox Tee adapter to the 5” Touch Display.
      2. The NMEA 2000 cable must be routed and installed in the vessel from the Seakeeper 6 wire harness CAN Tee to the Tee Adapter at the Seakeeper 5” Touch Display, included with P/N 904670.
    3. Install Seakeeper 5″ Touch Display equipment:
      1. Console space required: Approx. 5.24 W x 3.70 H in. (133 x 94 mm)
      2. Mounting Instructions, Surface Mount: see Envelope and Mounting Details, in Drawing No. 90438 – 5” Display Envelope and Mounting Details.
    4. CAN communications tee adapter and terminator mounting instructions:
      1. Console space required, Rear: Approx. 4 W x 3 H in. (102 x 76 mm)
      2. Mounting Instructions: Rear mount on vessel console panel, within 2 ft (0.6 m) of Display.
      3. Hardware required: One mounting screw for 0.197 in. (5 mm) diameter mounting hole on Tee Adapter.
    5. Connect Seakeeper 5” Touch Display Equipment:
      1. The Seakeeper 5” Touch Display is connected in accordance with figure below.
    6. The USB Extension Cable is 6.5 ft (2 m) long cable that enables software updating on a 5″ Touch Display where accessibility to rear panel is limited.
    ConnectBox Connected to Optional Seakeeper 5″ Touch Display

    NMEA 2000 Network Connection

    The Seakeeper 6 / 5 requires a connection to the vessel’s NMEA 2000 network backbone via a drop cable for access to the GPS signal. The Seakeeper 6 will monitor information on the NMEA network to support and optimize the performance of the Seakeeper 6. If no GPS signal is detected, a warning will appear on the Seakeeper display. The Seakeeper will not spool-down, but the operation of the unit will be limited until the GPS signal returns.

    1. Install customer-supplied NMEA 2000 Tee Adapter (space required: approximately 4 W X 3 H in. (102 X 76 mm).
    2. Connect NMEA Backbone to Tee Adapter.
      NOTE: NMEA drop cable can be no longer than 19.6 ft (6 m) in length.
    3. Connect Seakeeper-supplied NMEA cable (P/N: 30332) to the customer-supplied NMEA 2000 Tee Adapter on vessel’s NMEA 2000 backbone.
      1. An active NMEA 2000 compatible GPS signal is required on the vessel’s NMEA 2000 backbone to operate the Seakeeper 6.
        • If no GPS signal is detected, a Speed Over Ground (SOG signal) warning will be present on the Seakeeper app. See TB-90640 for NMEA connectivity guidance.

    ConnectBox Helm Mounting – Optional

    1. Console space required: Approx. 3.41 L x 4.15 W in. (87 x 106 mm).
    2. Mounting Instructions, Surface Mount: See Drawing No. 90558 – Seakeeper ConnectBox Helm Mounting Kit, for details. Seakeeper ConnectBox 3D Model available upon request.
    3. Mount ConnectBox Replacement Blank insert into Seakeeper 6 / 5 top cover at the original location of the ConnectBox.

    4.0 Cooling Installation

    4.1 Cooling Installation Introduction

    The Seakeeper 6 is shipped with the cooling circuit filled and ready for use. Only a quick confirmation of glycol level is required.

    Reference Documents & Drawings:


    Figure 1 Seakeeper 6 Cooling Components and Loads

    4.2 Installation Considerations

    1. Installer is responsible for supplying a dedicated seawater pump and associated plumbing. Seawater connections on the heat exchanger mate with ¾ in. (19 mm) hose. An optional seawater pump can be purchased through Seakeeper, P/N30331.
    2. There is no need to disconnect hose from glycol pump except to replace the pump. In this case, provision will need to be made to catch draining glycol as plumbing is disconnected. Use caution to avoid breaking plastic hose connections on pump casing.
    3. The seawater pump is powered by Cable 5, via “SW Pump 12 VDC Out” on the Seakeeper 6, as outlined in Electrical Installation Section.
      • This pump must operate on 12 VDC, 15 A OR 24 VDC, 10 A power. Pumps requiring other voltages or higher current can still be controlled by using this supply to trigger an installer-supplied contactor but a separate source of power must be provided.
    4. A dedicated through-hull fitting should be installed for each Seakeeper unit onboard the vessel to ensure sufficient seawater flow to each unit.
    5. It is recommended that the seawater pump is located below the waterline, as close to the baseline of the vessel as practically possible, to maintain positive inlet pressure on the pump in all operating conditions.
    6. A self-priming seawater pump is recommended to maintain water flow in all underway conditions. Cavitation can occur at the seawater inlet and potentially cause an air-lock condition restricting seawater flow to the heat exchanger.
    7. Vented loops are optional and should only be considered with centrifugal style pumps. Self-priming or positive displacement style pumps do not require a vented loop, this includes Seakeeper P/N 30331.
    8. Maximum seawater pressure in heat exchanger is 20 psi (1.4 bar)
    9. Seawater flow requirement through heat exchanger is 2.5 GPM (9.5 LPM) minimum and 8 GPM (30.3 LPM) maximum under all operating conditions of the boat. When sizing seawater pump, installer should factor in losses for raw water plumbing. In addition to initial operation at dock, new installations should be checked to be within the flow requirements while vessel is at speed. Flows higher than 8 GPM (30.3 LPM) could affect heat exchanger life.

    4.3 Connecting Seawater to Heat Exchanger

    Connecting Seawater to Heat Exchanger

    Refer to Figure 4 for typical seawater plumbing arrangement.

    Figure 4 – Typical Seawater Plumbing Arrangement

    1. Connect seawater pump to Seakeeper dedicated through-hull fitting. A strainer and seacock valve should generally be installed between the seawater inlet and the pump.
    2. Connect seawater from installer-supplied pump to lower ¾ in. (19 mm) hose barb on heat exchanger. Use the same practices as other below waterline seawater plumbing. Required flow rate is 2.5 GPM (9.5 LPM) minimum and 8 GPM (30.3 LPM) maximum.
    1. Connect seawater discharge (upper hose barb) to overboard drain. Use the same practices as other below waterline seawater plumbing.
    2. In addition to initial operation at dock, new installations should be checked for minimum 2.5 GPM (9.5 LPM) flow while vessel is at speed and when backing down.
      • If no other method of confirming flow is available, discharge line may be temporarily diverted to a bucket. Flow is calculated from time to fill a known volume.
      • A self-priming seawater pump (customer/installer supplied) may be required due to installation location to maintain water flow in all underway conditions where cavitation may occur and potentially cause an air-lock condition restricting seawater flow to the heat exchanger.
    3. Inspect raw water plumbing after sea trial for any signs of leakage.
    4. Heat exchanger contains removable end-caps to provide access for cleaning the tube bundle.

    Seakeeper Optional DC Seawater Pump (P/N 30331)

    1. Seakeeper offers a self-priming DC Seawater pump as an optional addition, P/N 30331– DC Seawater Pump Assembly, shown in Figure 6.
    2. The Seakeeper Seawater Pump is a 24 VDC pump operated at 12 VDC for the Seakeeper 6.
    3. The pump assembly is pre-wired for connection to Seakeeper 6 Cable 5 and includes a seawater strainer and various fittings. The pump specifications are as follows:

    NOTE: Use only SeaFlo-provided threaded fittings for DC Seawater Pump 30331.

    Volts24 VDC (operate at 12 V for Seakeeper 6)
    Rated Flow2.5 – 8 GPM (9.5 – 30.3 LPM)
    Overcurrent Protection Rating15 A
    Ignition ProtectionISO 8846 or equivalent
    Figure 6Seakeeper 6 DC Seawater Pump (P/N 30331)

    4.4 Adding Coolant

    1. Cooling system is filled to proper level when shipped, with a mixture of 50% ethylene glycol and 50% distilled water. The clear tube between heat exchanger and reservoir should be filled with green coolant mixture. If level has dropped, check for evidence of leaks at all connections before adding fluid as described below. If coolant is at the correct level, skip to Section: Connecting Seawater to Heat Exchanger.
    Figure 3 Seakeeper 6 Coolant Level
    1. Mix 50% ethylene glycol with 50% distilled water in a clean container. Refer to Table 1 or glycol manufacturer’s literature for freezing points.
    1. Pour mixture in until level reaches two-thirds of reservoir as shown in Figure 3. Filling reservoir above this level will not cause any damage but coolant may be expelled from pressure relief port in cap due to normal thermal expansion of coolant.
    2. Connect 12 V to controller.
      1. At the Display check for any ALARMS

      2. Press the POWER ON/OFF button.
      3. The flywheel will start to spin and the glycol pump will start.
      4. Recheck glycol level with fluid circulating in coolant circuit. Sight down inside reservoir and check that coolant level is above upper port on reservoir as shown in Figure 3. Replace cap.
      5. After several minutes of running, press POWER ON/OFF button to turn power off to the flywheel and glycol pump. The glycol pump will stop and the flywheel will coast to a stop.
    3. The cooling system is self-purging. If small amounts of air are in the system, they will most likely be dislodged during the first sea trial. Re-check level after sea trial and add fluid if required.

    5.0 Installation Requirements

    5.1 Installation Requirements Introduction

    The Installation Requirements section outlines the components and tools needed for the Seakeeper 6 / 5 installation that are not included within the scope of supply.

    5.2 Required Supplies for Seakeeper Installation

    Table 1 outlines the customer-supplied components required for the Seakeeper 6 / 5 installation:

    ItemDescriptionQTYInstallation Manual Reference SectionOther ReferenceSystem
    1Spreader bar for lifting the Seakeeper1Transport & UnpackingP/N 80067Mechanical
    2Seakeeper 6 Fixture Kit1Bolt-In InstallationP/N 90392Mechanical
    3Threaded insert M16-2 (24 mm)16Bolt-In InstallationDwg 90398Mechanical
    4Seakeeper 6/5 Bolt-In Kit1Bolt-In InstallationP/N 90400Mechanical
    5Seakeeper 6/5 Thru-Bolt Kit1Bolt-In InstallationP/N 90660Mechanical
    6Marine SealantARBolt-In InstallationDwg 90398Mechanical
    7Nickel-based Anti-seizeARBolt-In InstallationDwg 90398Mechanical
    8Circuit Breaker 30 A, 110 VAC
    or
    Circuit Breaker 20 A, 230 VAC
    1Electrical Equipment Power ConnectionsDwg 90396Electrical
    9Circuit Breaker, 12 VDC, 15 A2Electrical Equipment Power ConnectionsDwg 90396Electrical
    10Battery Isolator Switch1Electrical Equipment Power ConnectionsDwg 90396Electrical
    11M6 terminal lug for grounding Seakeeper1Electrical Equipment Ground ConnectionsDwg 90396Electrical
    12Cable, 10 AWG, for grounding Seakeeper at rear brace to vessel ground 1Electrical Equipment Ground ConnectionsDwg 90396
    ABYC E-11
    Electrical
    13Seawater pump, 12VDC, 15 A max Optional: DC Seawater Pump Assembly (pre-wired) 1Electrical Equipment Power ConnectionsDwg 90396
    P/N 30331
    Electrical / Cooling
    14Compatible MFD or Optional Seakeeper 5″ Touch Display1Electrical Equipment Power ConnectionsDwg 90396
    TB-90640 / P/N 90600
    Electrical
    15Through-hull fittings (1 high-speed pick-up / 1 overboard discharge)2Connecting Seawater to Heat ExchangerDwg 90397Cooling
    16Seawater Strainer *included with Seakeeper Seawater Pump (P/N 30331)1Connecting Seawater to Heat ExchangerDwg 90397Cooling
    17Seacock Valve1Connecting Seawater to Heat ExchangerDwg 90397Cooling
    183/4 in. (19 mm) ID Seawater Suction Hose AND Discharge HoseARConnecting Seawater to Heat ExchangerDwg 90397Cooling
    19Hose clamps for seawater plumbing to ¾ in. (19 mm) hose barb (2 per hose barb)4Connecting Seawater to Heat ExchangerDwg 90397Cooling

    AR = As Required
    Dwg = Drawing

    5.3 Tools Required for Installation

    ItemDescriptionUse
    1Wire CutterDC and AC power cables
    2Wire StripperDC and AC power cables
    310 and 13 mm Socket WrenchSide Panels and ground stud
    4Slot Screwdriver, 5/64 in.Field assembly connectors
    51/4 in. Nut DriverHose clamps
    6Greenlee K05-Synchro Crimp Tool, or equivalentGround cable
    7Utility KnifeScoring cable jackets
    8Hoist, Forklift, or CraneUnpacking and Lifting Seakeeper 4.5 into position
    9Drill/Drill PressBolt hole penetrations
    101/2 in. Drive Torque WrenchFoundation bolt torqueing
    1119 mm Socket WrenchFoundation bolts
    12Heat GunFor conductor heat shrink
    13Hole SawThrough-hull seawater fittings
    NOTE: Additional tools could be required for the installation of customer-supplied components.

    6.0 Installation and Start Up Checklist

    6.1 Checklists Introduction

    Reference Documents:

    The Installation and Start Up Checklist section provides an overview of the primary steps covered in the installation manual and should be referenced throughout the installation process. Upon completion of the
    Seakeeper 6 / 5 installation, the installer should commission each Seakeeper unit with the Seakeeper Commissioning Form (90437). The Commissioning Checklist Work Instruction (SWI-105) provides a checklist of items to inspect and verify during the commissioning process and serves as a supplement to the Seakeeper
    Commissioning Form (90437).

    All Seakeeper stabilizers should be commissioned to verify installation specifications and requirements have been implemented properly. The commissioning process should include completion of the Seakeeper
    Commissioning Form (90437), all the items in the Installation Checklist, and verification of Seakeeper operation without alarms or abnormal behavior.


    6.2 Installation Checklist

    Please Complete Checklist and E-mail to support@seakeeper.com or telefax to +1.410.326.1199

    6.1.1 Mechanical Checklist
    (Reference Installation Manual Section: Mechanical Installation)

    • Seakeeper foundation installed in hull
    • Foundation bolts torqued to specification

    6.1.2 Electrical Checklist
    (Reference Seakeeper Drawing No. 90396 – Seakeeper 5/6 Cable Block Diagram & Installation Manual Section: Electrical Installation)

    Mount Components

    • Display (near helm)

    Connect Customer Supplied Cables

    • Cable 3 (Customer Supplied)
      • Install lugs on both ends of customer-supplied 10 AWG ground cable
      • Connect one end of Cable 3 to nearest vessel ground and other end to Seakeeper rear brace

    Connect Seakeeper Supplied Cables

    • Cable 1 (Seakeeper Supplied)
      • Connect other end of Cable 1 to 12 VDC power at customer-supplied connection box or directly to circuit breaker
      • Plug connector of Cable 1 into mating connector on Seakeeper wire harness
    • Cable 9 (Seakeeper Supplied)
      • Connect Cable 9 from SW PUMP VDC IN directly to circuit breaker
    • Cable 5 (Seakeeper Supplied)
      • Connect Cable 5 from SW PUMP VDC OUT to customer-supplied 12 VDC seawater pump
    • Cable 4 (Seakeeper Supplied)
      • Connect female end of CAN communications Cable 3 to mating connector on Seakeeper wire harness
      • Route CAN communications Cable 3 from Seakeeper to helm (male end goes to helm)
      • Connect male end of CAN communications Cable 4 at helm to CAN Tee Adapter
      • Connect Display and Seakeeper-supplied Cable 4 to CAN Tee Adapter with CAN Terminator

    6.1.3 Cooling Checklist
    (Reference Installation Manual Section: Cooling Installation)

    • Verify coolant level just below filler neck in heat exchanger coolant reservoir.
    • Connect seawater hoses / open sea cocks to heat exchanger and test seawater pump.
    • Verify 2.5 GPM (9.5 LPM) minimum and 8 GPM (30 LPM) maximum seawater flow through heat exchanger under all operating conditions of the boat.

    6.1.4 Start Up Checklist
    (Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)

    • Remove lifting bolts and install cover panels
    • Turn on 12 VDC circuit breakers (one for power and one for 12 VDC SW Pump)
    • Turn on 110-230 VAC circuit breaker
    • Verify display works and no ALARMS are present
    • Follow instructions in Installation Manual Section: Start Up Instructions to turn on the Seakeeper
    • Verify seawater pump eventually turns on when the Seakeeper is ON
    • Verify that no ALARMS are present
    • Follow instructions in Installation Manual Section: Start Up Instructions to turn off the Seakeeper
    • AC & DC power and seawater pump may be turned off after the Seakeeper is turned off by placing the Seakeeper in LOCK mode and turning the Seakeeper off
    • Seakeeper takes 4 or more hours to coast down to 0 RPM from full speed

    6.3 Start Up Checklist

    Refer to Seakeeper 6 / 5 Operation Manual for detailed start up instructions.


    Prior to beginning the start up sequence all previous Sections of the Installation Manual for Mechanical, Electrical, and Cooling installation must be complete.

    Before continuing, the Seakeeper cover must be installed and the operating clearances must be clear of personnel and equipment.

    CHECKREQUIREMENT TO BE MET
    Remove lifting eyebolts and install sealing bolts and flat washers into lifting eyeholes and install top cover panels.
    Supply 110-230 VAC to Motor Drive Box at customer-supplied electrical disconnect.
    Energize low-current 15 A breaker, and seawater pump breaker.
    Verify ConnectBox and MFD / 5″ Touch Display is active and no alarms present.
    Check that battery voltage exceeds 12 VDC.
    Override seawater pump “ON” for 5 seconds) and verify flow at seawater outlet.
    (To activate override, at 0 RPM flywheel speed, hold down SERVICE button wrench icon for 5 seconds to reveal override screen)
    Deactivate seawater pump when completed obtaining seawater flow rate.
    Press Seakeeper ON/OFF Button and follow instructions in Seakeeper Operation Manual for complete start-up instructions.
    Verify no alarms are present.
    Power Seakeeper down, the Seakeeper flywheel will take 2+ hours to coast down
    to 0 RPM.

    7.0 Revision History

    REVISIONDESCRIPTIONDATE
    4Cooling system updated. MFD compatibility updated.
    Minor update edits.
    03MAR2023
    5Added ConnectBox integration and associated installation steps. Updated images for ConnectBox introduction. Minor edits. Added crate stacking recommendations28JUL2023