5.0 Installation Requirements

5.1 Installation Requirements Introduction

This section describes the first start up of the Seakeeper.

Reference Documents & Drawings:
Link to Seakeeper manuals

  • 90266 – Seakeeper 26 Operation Manual

  • Previous sections for mechanical, electrical and cooling installation must be completed before this start up sequence is initiated.
  • Before continuing, covers must be installed unless the Seakeeper is inaccessible and there is no risk to injury. Also, the area around the Seakeeper must be clear of personnel and equipment.

5.2 Required Supplies for Seakeeper Installation

(Not Supplied With the Seakeeper)

ItemDescriptionQtyInstallation Manual Reference SectionOther ReferenceSystem
1Adhesive and cleaning supplies for bonding to hullMechanical InstallationMechanical
2Soundproofing ConsiderationsSelection of Installation LocationMechanical
3Spreader bar for lifting SeakeeperTransport and UnpackingP/N 80029Mechanical
4Circuit Breaker, AC, 2-Pole,
30 A
1Electrical Equipment Power ConnectionsDwg 90310Electrical
5Circuit Breaker, DC, 1-Pole,
15 A
1Electrical Equipment Power Connections Dwg 90310Electrical
6M6 terminal lug for grounding Seakeeper at rear brace1Electrical Equipment Ground ConnectionsElectrical
7Cable, 10 AWG, for grounding Seakeeper at rear brace to vessel ground ARElectrical Equipment Ground Connections Dwg 90310Electrical
8Sili-Thane 803 Marine Sealant (or equivalent)ARBolt-In Installation, Installation of Seakeeper and
Saddle Installation, Installation of Seakeeper
Mechanical
9Nickel-based Anti-SeizeARBolt-In Installation, Installation of Seakeeper and
Saddle Installation, Installation of Seakeeper
Mechanical
10Seawater Pump, 24 VAC1Electrical Equipment Power Connections Dwg 90320Electrical
11Relay for seawater pump control (Not required if using 230 VAC pump)1Electrical Equipment Power Connections Electrical
12¾ in. (19 mm) ID seawater hoseARCooling InstallationDwg 90320Cooling
13Hose clamps for seawater plumbing to ¾ in. (19 mm) hose barb (2 per hose barb)4Cooling Installation Dwg 90320Cooling
14Through-hull fittings (1 high-speed pick-up / 1 overboard discharge)2Cooling Installation Dwg 90320Cooling
15Seawater strainer1Cooling Installation Dwg 90320Cooling
16Seacock valve1Cooling Installation Dwg 90320Cooling
17Flow restriction valve (optional)1Cooling Installation Dwg 90320Cooling

AR = As Required
Dwg = Drawing