Seakeeper 26 Installation Manual (90265-8); S/N 26-233-0690 to Current
6.3 Start Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)
- Remove lifting eye bolts, replace with sealing screw/washers provided, and install cover panels
- Turn on 24 VDC circuit breaker
- Turn on 230 VAC circuit breaker
- Verify display works and no ALARMS are present
- If display does not work, turn off both circuit breakers immediately.
- Check polarity of 24 VDC power per Section: Electrical Equipment Power Connections – DC Power Connection Instructions.
- Follow instructions in Section: Start Up Instructions to turn on the Seakeeper
- Verify seawater pump turns on when the Seakeeper is turned ON
- Verify that no ALARMS are present
- Follow instructions in Section: Start Up Instructions to turn off the Seakeeper
- AC & DC power and seawater pump may be turned off after the Seakeeper is turned off by placing the Seakeeper in LOCK mode and turning the Seakeeper off.
- Seakeeper 26 takes 6+ hours to coast down to 0 RPM from full speed