6.1 Start Up Introduction

This section describes the first startup of the Seakeeper.

Reference Documents & Drawings:
Link to Seakeeper 9/7HD Reference Documents

  • 90223 – Seakeeper 9 Operation Manual
  • Previous sections for mechanical, electrical and cooling installation must be completed before this startup sequence is initiated.
  • Before continuing, covers must be installed unless the Seakeeper is inaccessible and there is no risk to injury. Also, the area around the Seakeeper must be clear of personnel and equipment.