6.0 Installation Checklist and Required Supplies

6.1 Installation Checklist

Please Complete Checklist and E-mail to support@seakeeper.com or telefax to +1.410.326.1199

6.1.1 Mechanical Checklist
(Reference Installation Manual Section: Mechanical Installation)

  • Seakeeper foundation installed in hull
  • Foundation bolts torqued to specification

6.1.2 Electrical Checklist
(Reference Seakeeper Drawing No. 90396 – Seakeeper 5/6 Cable Block Diagram & Installation Manual Section: Electrical Installation)

Mount Components

  • Display (near helm)

Connect Customer Supplied Cables

  • Cable 3 (Customer Supplied)
    • Install lugs on both ends of customer-supplied 10 AWG ground cable
    • Connect one end of Cable 3 to nearest vessel ground and other end to Seakeeper rear brace

Connect Seakeeper Supplied Cables

  • Cable 1 (Seakeeper Supplied)
    • Connect other end of Cable 1 to 12 VDC power at customer-supplied connection box or directly to circuit breaker
    • Plug connector of Cable 1 into mating connector on Seakeeper wire harness
  • Cable 9 (Seakeeper Supplied)
    • Connect Cable 9 from SW PUMP VDC IN directly to circuit breaker
  • Cable 5 (Seakeeper Supplied)
    • Connect Cable 5 from SW PUMP VDC OUT to customer-supplied 12 VDC seawater pump
  • Cable 4 (Seakeeper Supplied)
    • Connect female end of CAN communications Cable 3 to mating connector on Seakeeper wire harness
    • Route CAN communications Cable 3 from Seakeeper to helm (male end goes to helm)
    • Connect male end of CAN communications Cable 4 at helm to CAN Tee Adapter
    • Connect Display and Seakeeper-supplied Cable 4 to CAN Tee Adapter with CAN Terminator

6.1.3 Cooling Checklist
(Reference Installation Manual Section: Cooling Installation)

  • Verify coolant level just below filler neck in heat exchanger coolant reservoir.
  • Connect seawater hoses / open sea cocks to heat exchanger and test seawater pump.
  • Verify 2.5 GPM (9.5 LPM) minimum and 8 GPM (30 LPM) maximum seawater flow through heat exchanger under all operating conditions of the boat.

6.1.4 Start Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)

  • Remove lifting bolts and install cover panels
  • Turn on 12 VDC circuit breakers (one for power and one for 12 VDC SW Pump)
  • Turn on 110-230 VAC circuit breaker
  • Verify display works and no ALARMS are present
  • Follow instructions in Installation Manual Section: Start Up Instructions to turn on the Seakeeper
  • Verify seawater pump eventually turns on when the Seakeeper is ON
  • Verify that no ALARMS are present
  • Follow instructions in Installation Manual Section: Start Up Instructions to turn off the Seakeeper
  • AC & DC power and seawater pump may be turned off after the Seakeeper is turned off by placing the Seakeeper in LOCK mode and turning the Seakeeper off
  • Seakeeper takes 4 or more hours to coast down to 0 RPM from full speed

6.2 Required Supplies Needed for Seakeeper Installation

6.2.1 (Not Supplied With the Seakeeper)

ItemDescriptionQtyInstallation Manual Reference SectionOther ReferenceSystem
1Adhesive and cleaning supplies for bonding to hullMechanical InstallationMechanical
2Soundproofing ConsiderationsSelection of Installation LocationMechanical
3Spreader bar for lifting SeakeeperTransport and UnpackingMechanical
4Hose clamps for seawater plumbing to ¾ in. (19 mm) hose barb (2 per hose barb)4Connecting Seawater to Heat ExchangerCooling
5Circuit Breaker, AC, 2-Pole, (30 A to be used with 110-120 VAC, OR Nominal (± 10%), 20 A to be used with 208-230 VAC Nominal (± 10%))1Electrical Equipment Power ConnectionsDwg 90396Electrical
6Circuit Breaker, DC, 1-Pole, 15 A2Electrical Equipment Power ConnectionsDwg 90396Electrical
7M6 terminal lug for grounding Seakeeper at rear brace1Electrical Equipment Ground ConnectionsElectrical
8Cable, 10 AWG, for grounding Seakeeper at rear brace to vessel groundARElectrical Equipment Power ConnectionsDwg 90396Electrical
9Seawater pump, 12 VDC1Electrical Equipment Ground Connections Electrical
10Relay for seawater pump control (Not required if using Seakeeper output 12 VDC pump)1Electrical Equipment Power Connections Electrical

AR = As Required
Dwg = Drawing

6.2.2 List of Common Tools That May Be Required for Installation

ItemDescriptionUse
1Wire cutterDC Power, AC Power cables
2Wire stripperDC Power, AC Power cables
313 mm Socket WrenchCover Panels
4Phillips head screwdriver, 5/64 inchCover Panels
5Slot screwdriver, 5/64 inchField assembly connectors
6¼ in. nut driverHose clamps
7Terminal or quick disconnect crimperPower cables
8Utility knifeScoring cable jackets
910 mm Socket WrenchGround Stud