Seakeeper 40 Installation Manual (90715-1) 40-233-0001 - 40-234-0042
6.3 Start Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)
- Remove lifting eyes, install sealing fasteners in lifting holes, and install cover panels
- Turn on 24 VDC circuit breakers for control power and DC Seawater Pump
- Turn on 230 VAC circuit breaker
- Verify display works and no ALARMS are present
- If display does not work, turn off both circuit breakers immediately.
- Check polarity of 24 VDC power per Section: Electrical Equipment Power Connections – DC Power and Seawater Pump Connection Instructions.
- Follow instructions in Operations Manual Section: Start Up Instructions to turn on the Seakeeper
- Verify that no ALARMS are present
- Follow instructions in Section: Start Up Instructions to turn off the Seakeeper
- AC & DC power and seawater pump may be turned off after the Seakeeper is turned off by placing the Seakeeper in LOCK mode and turning the Seakeeper off.
- Seakeeper 40 takes 5+ hours to coast down to 0 RPM from full speed