Installation Checklist and Required Supplies

Installation Checklist

Mechanical Checklist
(Reference Installation Manual Section: Mechanical Installation)

  • Seakeeper foundation installed in hull
  • Seakeeper supplied foundation bolts torqued to specification
  • Clearances around Seakeeper meet specifications and no obstructions are within the Seakeeper envelope

Electrical Checklist
(Reference Seakeeper Drawing No. 90470 – Seakeeper 2 Cable Block Diagram & Installation Manual Section: Electrical Installation)

Mount Components

  • Display (near helm)

Connect Seakeeper and Customer Supplied Cables

  • Cable 7 (Seakeeper Supplied)
    • Connect Cable 7 from Seakeeper 12 VDC 15 A power at customer-supplied connection box, or directly to a circuit breaker.
    • Plug connector of Cable 7 into mating connector on the Seakeeper wire harness.
  • Cable 6 (Customer Supplied)
    • Install lugs on both ends of customer-supplied 4 AWG ground cable.
    • Connect one end of Cable 6 to nearest vessel ground and other end to Seakeeper foundation.

Connect Seakeeper Supplied Cables

  • Conductors 1&2 (Seakeeper Supplied)
    • Connect Conductors 1&2 from Drive Box to 12 VDC 100 A at customer-supplied connection box or directly to circuit breaker.
  • Cable 5 (Seakeeper Supplied)
    • Connect female end of Cable 5 to customer supplied 12 VDC 3 A seawater pump.
    • Plug male end connector of Cable 5 into mating connector on the Seakeeper wire harness
  • Cable 3 (Seakeeper Supplied)
    • Connect female end of CAN communications Cable 3 to mating connector on the Seakeeper wire harness
    • Route CAN communications Cable 3 from the Seakeeper to helm (male end goes to helm)
    • Connect male end of CAN communications Cable 3 at helm to CAN Tee Adapter
    • Connect Display and Seakeeper-supplied Cable 4 to CAN Tee Adapter with CAN Terminator

Cooling Checklist
(Reference Installation Manual Section: Cooling Installation)

  • Verify coolant level in heat exchanger coolant reservoir.
  • Connect seawater hoses / open sea cocks to heat exchanger and test seawater pump.
  • Verify 2 GPM (7.6 LPM) minimum and 6 GPM (22.7 LPM) maximum seawater flow through heat exchanger under all operating conditions of the boat. (The seawater pump output will operate for two minutes after the Seakeeper is turned on. During operation, the seawater pump output is turned on and off based on the temperature of the Seakeeper)

Start Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)

  • Remove lifting bolts and install cover panels
  • Turn on 12 VDC 15 A circuit breaker
  • Turn on 12 VDC 100 A circuit breaker
  • Verify display works and no ALARMS are present
    • If display does not work, turn off both circuit breakers immediately
    • Check polarity of 12 VDC 15 A power per Section 2.2.5
  • Follow instructions in Installation Manual Section: Start Up Instructions, to turn on the Seakeeper
  • Verify seawater pump turns on when the Seakeeper is turned ON
  • Verify that no ALARMS are present
  • Follow instructions in Installation Manual Section: Start Up Instructions, to turn off the Seakeeper
  • DC power and seawater pump may be turned off after the Seakeeper is turned off by placing the Seakeeper in LOCK mode and turning the Seakeeper off
  • Seakeeper 2 takes 16+ hours to coast down to 0 RPM from full speed

Required Supplies Needed for Seakeeper Installation

(Not Supplied With the Seakeeper)

ItemDescriptionQtyInstallation Manual Reference SectionOther ReferenceSystem
1Soundproofing ConsiderationsSelection of Installation LocationMechanical
2Spreader bar for lifting the Seakeeper1Transport and UnpackingMechanical
3Hose clamps for seawater plumbing to ¾ in. (19 mm) hose barb (2 per hose barb)4Connecting Seawater to Heat ExchangerCooling
4M6 terminal lug for grounding Seakeeper at rear brace1Electrical Equipment Ground Connections Dwg 90470 Electrical
5Cable, 4 AWG, for grounding Seakeeper at foundation to vessel ground (used with item 4)ARElectrical Equipment Ground Connections Dwg 90470Electrical
6Seawater pump, 12 VDC, 15A max1Electrical Equipment DC Pump Power Dwg 90470 Electrical
7Pump over current protection, per pump spec1Electrical Equipment DC Pump Power Dwg 90470 Electrical
8100 A Circuit breaker for Conductor 11Electrical Equipment High Current Power Input Dwg 90470 Electrical
915 A Circuit breaker for Cable 71Electrical Equipment Low Current Power Input Dwg 90470 Electrical

AR = As Required
Dwg = Drawing

List of Common Tools That May Be Required for Installation

ItemDescriptionUse
1Wire cutterDC Power cables
2Wire stripperDC Power cables
33 mm hex keyGimbal sensor mount plate
42.5 mm hex keyGimbal angle sensor
5¼ in. nut driverHose clamps
6Quick Cable 4245 Crimp Tool, Molex 19284-0034 Crimp Tool, or equivalentPower cables
7Utility knifeScoring cable jackets