6.2 Installation Checklist

Please Complete Checklist and e-mail to
support@seakeeper.com or emeasupport@seakeeper.com.

5.1.1 Mechanical Checklist
(Reference Installation Manual Section: Mechanical Installation)

_____ Seakeeper foundation installed in hull

_____ Foundation bolts torqued to specification


5.1.2 Electrical Checklist
(Reference Seakeeper Drawing No. 90257 – Seakeeper 9 Cable Block Diagram & Installation Manual Section: Electrical Installation)

Mount Components

_____ Display (near helm)


Connect Customer Supplied Cables

Seakeeper Ground Cable (Customer supplied)

_____ Install lugs on both ends of customer-supplied 10 AWG (6 mm2) ground cable

_____ Connect one end of ground cable to nearest vessel ground and other end to
Seakeeper 9 rear brace

Connect Seakeeper Supplied Cables

Control Power Cable

_____ Connect control power cable from Seakeeper to 24 VDC power at
customer-supplied connection box or directly to circuit breaker

_____ Plug connector of control power cable into mating connector on
Seakeeper wire harness

AC Input Cable

_____ Connect AC input cable from Drive Box to 230 VAC single phase at
customer-supplied connection box or directly to circuit breaker

DC Seawater Pump Power Cable

_____ Connect DC seawater pump power input cable from Seakeeper
to 24 VDC /10 A power at customer-supplied connection box or
directly to circuit breaker

_____ Plug connector of DC seawater pump power cable into mating
connector on Seakeeper wire harness at DC SW Pump In

DC Seawater Pump Output Cable

_____ Connect seawater pump output cable from DC SW Pump Out to
Y-Branch SW Pump Output & Valve Cable

_____ Connect seawater pump and electric valve to Y-Branch SW Pump
Output & Valve Cable

MFD Ethernet Adapter Cable

_____ Connect male end of ethernet adapter cable to Ethernet
connection on ConnectBox

_____ Route ethernet adapter cable to selected MFD compatibility
cable towards helm

_____ Connect female end of ethernet adapter cable to MFD
compatibility cable

_____ Connect MFD compatibility cable to MFD Display

OPTIONAL Seakeeper 5″ Display CAN Cable

_____ Connect female end of CAN communication cable to
tee-adapter at ConnectBox (at tee-adapter terminal resistor)

_____ Route CAN communication cable to Seakeeper 5″ display

_____ Connect male end of CAN communication cable to
tee-adapter with terminal resistor at 5″ display


5.1.3 Cooling Checklist
(Reference Installation Manual Section: Cooling Installation)

_____ Verify coolant level in coolant reservoir

_____ Connect seawater hoses / open sea cocks to heat
exchanger and test seawater pump

_____ Verify 4 GPM (15 LPM) minimum and 8 GPM (30 LPM)
maximum seawater flow through heat exchanger under
all operating conditions of the boat


5.1.4 Start Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)

_____ Remove lifting eyebolts and install cover panels

_____ Turn on 24 VDC circuit breakers

_____ Turn on 230 VAC circuit breaker

_____ Verify display works and no ALARMS are present

_____ If display does not work, turn off both circuit breakers
immediately

_____ Check polarity of 24 VDC power per Section 3.4

_____ Follow instructions in Installation Manual Section: Start Up
Instructions to turn on the Seakeeper

_____ Verify seawater pump turns on while the Seakeeper
is turned ON

_____ Verify no ALARMS are present

_____ Follow instructions in Installation Manual Section: Startup
Instructions to turn off the Seakeeper

_____ AC & DC power and seawater pump may be turned off
after the Seakeeper is turned off by placing the
Seakeeper in LOCK mode and turning the Seakeeper off

_____ Seakeeper 9 takes 4+ hours to coast down to 0 RPM from full speed