Seakeeper 9 Installation Manual (90222-12); S/N 9-254-5731 to Current
2.5.3 Hull Preparation
- Position installation fixture (Figure 17) on hull girders noting recommended clearances for maintenance from Figure 3 & 4 (in Section 2.2: Selection of Installation Location). Check that the screws fastening the saddles to the installation fixture are tight (Fig. 18).

- Mask hull area (Fig. 18) around foundation saddles for easy clean-up and to create outline of surface area to receive adhesive as (Fig. 17). Ensure that the bond gap is within Seakeeper’s recommended thickness, or 3 mm if using Plexus MA590.

- Raise fixture clear of foundation. Check all four mounting areas are co-planar to within 0.13 in. (3 mm) to each other, as well as parallel to the water line plane, as shown in Figure 17 and 19.

- Thoroughly clean with alcohol or acetone all areas of girders to be bonded to remove any contaminates. Use new paper towels for cleaning, not shop rags.
- Remove any paint or gel-coat from bond surfaces so that adhesive will bond directly to laminate fibers and resin as shown in Figure 19.
- Thoroughly sand girder bond surfaces with 80 grit sandpaper. (IMPORTANT – BOND STRENGTH MAY BE REDUCED IF THIS STEP IS SKIPPED.)
- Wipe surfaces clean from dust with alcohol or acetone using new paper towels, not shop rags.
- Re-position installation fixture on girders and double-check that the adhesive gap is within the adhesive manufacturer’s maximum recommended thickness. Seakeeper recommends a maximum gap of 3 mm if using Plexus MA590.
Note: if bonding saddles to a metal structure, follow adhesive manufacturer instructions for metal substrates.