Seakeeper 40 Installation Manual (90715-4) 40-254-0200 to Current
6.2 Installation Checklist
Please Complete Checklist and E-mail to support@seakeeper.com or emeasupport@seakeeper.com (outside of the Americas).
Mechanical Checklist
(Reference Installation Manual Section: Mechanical Installation)
Seakeeper foundation installed in hull
Foundation bolts torqued to specification
Electrical Checklist
(Reference Seakeeper Drawing No. 90710 – Seakeeper 40 Cable Block Diagram & Installation Manual Section: Electrical Installation)
Mount Components
Multifunction Display (at helm)
Remote ConnectBox mounting: ______________________ (location)
Connect Customer Supplied Cables
Ground Cable (Customer Supplied)
Install lugs on both ends of customer-supplied 10 AWG ground cable
Connect one end of Ground Cable to nearest vessel ground and other end to Seakeeper foundation frame
Connect Seakeeper Supplied Cables
DC Input Power Cable (Seakeeper supplied)
Connect the DC Input Power Cable from Seakeeper to 24 VDC power at customer-supplied connection box or directly to circuit breaker
Plug connector of DC Input Power Cable into mating connector on Seakeeper wire harness
AC Power Input Cable (Seakeeper Supplied)
Connect the AC Power Input Cable from Drive Box to 230 VAC single phase at customer-supplied connection box or directly to circuit breaker
CAN Communication Assembly (Seakeeper Supplied)
Connect female end of CAN communications Cable to mating connector on Seakeeper wire harness
Route CAN communications Cable from Seakeeper to helm (male end goes to helm)
Connect male end of CAN communications Cable at helm to CAN Tee Adapter
Connect Display and Seakeeper-supplied 24 in. (0.6 m) cable to CAN Tee Adapter with CAN Terminator
Seawater Pump Power Output Cable (Seakeeper Supplied)
Connect Seawater Pump Power Output Cable from Seakeeper wire harness to customer-supplied 24 VDC seawater pump
Seawater Pump Power Input Cable (Seakeeper supplied)
Connect the Seawater Pump Power Input Cable from Seakeeper DC SW Pump In to 24 VDC power at customer supplied connection box or directly to circuit breaker
Cooling Checklist
(Reference Installation Manual Section: Cooling Installation)
Verify coolant level in heat exchanger coolant reservoir.
Connect seawater hoses / open sea cocks to heat exchanger and test seawater pump.
Verify 13 GPM (49 LPM) minimum and 15 GPM (57 LPM) maximum seawater flow through heat exchanger under all operating conditions of the boat.