5.0 Installation Requirements

5.1 Installation Requirements Introduction

The Installation Requirements section outlines the components and tools needed for the Seakeeper 14 installation that are not included within the scope of supply.

5.2 Required Supplies and Tools for Installation

5.2.1 Required Supplies Needed for Seakeeper Installation
(Not Supplied with the Seakeeper)

ItemDescriptionQtyInstallation Manual Reference SectionOther ReferenceSystem
1Adhesive and cleaning supplies for bonding to hullARMechanical Installation Mechanical
2Soundproofing ConsiderationsARSelection of Installation LocationMechanical
3Spreader bar for lifting Seakeeper1Transport and UnpackingP/N 11015Mechanical
4Threaded insert: M16-2 x 1 DIA (24 mm)16Mechanical Installation Dwg 90255Mechanical
5Marine SealantARMechanical Installation Dwg 90255Mechanical
6Nickel-Based Anti-Seize (SAF-T-EZE SBT-4N, or similar)ARMechanical InstallationDwg 90255Mechanical
7Circuit Breaker, AC, 2-Pole, 30 A1Electrical Equipment Power ConnectionsDwg 90257Electrical
8Circuit Breaker, DC, 1-Pole, 10 A, Gyro Controller1Electrical Equipment Power Connections Dwg 90257Electrical
9Circuit Breaker, DC, 1-Pole, 10 A max, Seawater Pump1Electrical Equipment Power ConnectionsDwg 90257Electrical
10M6 terminal lug for grounding Seakeeper at rear brace1Electrical Equipment Ground ConnectionsDwg 90257Electrical
11Marine Cable, Green, 10 AWG, ground connection (used with item 11)ARElectrical Equipment Ground Connections Dwg 90257Electrical
12Seawater pump, 24 VDC1Electrical Equipment Power Connections Dwg 90257Electrical
13Y-Branch Seawater Pump Output & Valve Kit (P/N 90971) (Supplied by Seakeeper)1Electrical Equipment Power ConnectionsDwg 90257Electrical
14Relay for seawater pump control (Not required if using 24 VDC pump)1Electrical Equipment Power Connections Electrical
15Compatible MFD or Optional Seakeeper 5″ Touch Display1Electrical Equipment Power Connections Dwg 90257Electrical
16Through-hull fittings (1 pick-up, 1 overboard discharge)2Cooling InstallationDwg 90251Cooling
17Seacock Valve1Cooling InstallationDwg 90251Cooling
18Seawater Strainer (Included with Seakeeper Seawater Pump P/N 30322)1Cooling InstallationDwg 90251Cooling
193/4 in. ID Seawater HoseARConnecting SeawaterDwg 90251Cooling
20Hose clamps for seawater plumbing to ¾ in. (19 mm) hose barb (2 per hose barb)ARConnecting SeawaterDwg 90251Cooling

AR = As Required
Dwg = Drawing

5.2.2 List of Common Tools That May Be Required for Installation

ItemDescriptionUse
1Wire cutterDC Power, AC Power cables
2Wire stripperDC Power, AC Power cables
313 mm Socket Side Panels
424 mm SocketFoundation bolts
53 mm hex keyGimbal sensor mount plate
62.5 mm hex keyGimbal angle sensor
7¼ in. Nut DriverHose clamps
8Terminal or quick disconnect crimperPower cables
9Utility KnifeScoring cable jackets
1010 mm Socket Ground Stud and side panels
11Hoist, Forklift, or CraneUnpacking and lifting Seakeeper 9 into position
12Drill / Drill PressBolt hole penetrations for bolt-in installations
13Threaded Insert Installation KitTap and install threaded inserts for bolt-in installation
141/2″ Drive Torque WrenchFoundation bolts
15Fish TapeCable pulls
16Hole SawThru-hull fittings