Seakeeper 10 Installation Manual (90841-1)
6.1 Checklists Introduction
This section describes the first startup of the Seakeeper.
Reference Documents & Drawings:
- 90842 – Seakeeper 10 Operation Manual
- 90437 – Seakeeper Commissioning Form
- 90569 – Seakeeper ConnectBox and App Quick Start Guide
- SWI-105 – Commissioning Checklist

- Previous sections for mechanical, electrical, and cooling installation must be completed before initiating this startup sequence.
- Before continuing, covers must be installed unless the Seakeeper is inaccessible and there is no risk of injury. Also, the area around the Seakeeper must be clear of personnel and equipment.
The Installation and Start-Up Checklist section provides an overview of the primary steps covered in the installation manual and should be referenced throughout the installation process. Upon completion of the
For the Seakeeper 10 installation, the installer should commission each Seakeeper unit with the Seakeeper Commissioning Form (90437). The Commissioning Checklist Work Instruction (SWI-105) provides a checklist of items to inspect and verify during the commissioning process and serves as a supplement to the Seakeeper
Commissioning Form (90437).
All Seakeeper stabilizers should be commissioned to verify that installation specifications and requirements have been appropriately implemented. The commissioning process should include completing the Seakeeper Commissioning Form (90437), reviewing all the items in the Installation Checklist, and verifying that the Seakeeper operation is without alarms or abnormal behavior.