6.2 Installation Checklist

Please Complete Checklist and E-mail to
customerservice@seakeeper.com or telefax to +1.410.326.1199

6.2.1 Mechanical Checklist
(Reference Installation Manual Section: Mechanical Installation)

_____ Seakeeper foundation installed in hull

_____ Foundation bolts torqued to specification


6.2.2 Electrical Checklist
(Reference Seakeeper Drawing No. 90257 – Seakeeper 10 Cable Block Diagram & Installation Manual Section: Electrical Installation)

Mount Components

_____ Optional 5″ Display (near helm or in an accessible location)


Connect Customer Supplied Cables

Seakeeper Ground Cable (Customer supplied)

_____ Install lugs on both ends of customer-supplied 10 AWG (6 mm2) ground cable

_____ Connect one end of ground cable to nearest vessel ground and other end to Seakeeper 10 rear
brace

Connect Seakeeper Supplied Cables

Control Power Cable

_____ Connect control power cable from Seakeeper to 24 VDC power at customer-supplied connection
box or directly to circuit breaker

_____ Plug connector of control power cable into mating connector on Seakeeper wire harness

AC Input Cable

_____ Connect AC input cable from Drive Box to 230 VAC single phase at customer-supplied connection
box or directly to circuit breaker

DC Seawater Pump Power Cable

_____ Connect DC seawater pump power input cable from Seakeeper to 24 VDC /10 A power at customer-
supplied connection box or directly to circuit breaker

_____ Plug connector of DC seawater pump power cable into mating connector on Seakeeper wire
harness at DC SW Pump In

DC Seawater Pump Output Cable

_____ Connect seawater pump output cable from DC SW Pump Out to 24 VDC seawater pump

MFD Ethernet Adapter Cable

_____ Connect male end of ethernet adapter cable to Ethernet connection on ConnectBox

_____ Route ethernet adapter cable to selected MFD compatibility cable towards helm

_____ Connect female end of ethernet adapter cable to MFD compatibility cable

_____ Connect MFD compatibility cable to MFD Display

OPTIONAL Seakeeper 5″ Display CAN Cable

_____ Connect female end of CAN communication cable to tee-adapter at ConnectBox
(at tee-adapter terminal resistor)

_____ Route CAN communication cable to Seakeeper 5″ display

_____ Connect male end of CAN communication cable to tee-adapter with terminal resistor at 5″ display


6.2.3 Cooling Checklist
(Reference Installation Manual Section: Cooling Installation)

_____ Verify coolant level in coolant reservoir

_____ Connect seawater hoses / open sea cocks to heat exchanger and test seawater pump

_____ Verify 4.5 GPM (17 LPM) minimum and 6 GPM (22.7 LPM) maximum seawater flow through heat
heat exchanger under all operating conditions of the boat


6.2.4 Start-Up Checklist
(Reference Installation Manual Section: Start Up & Operation Manual Section: System Operation)

_____ Remove lifting eyebolts and install cover panels

_____ Turn on 24 VDC circuit breakers

_____ Turn on 230 VAC circuit breaker

_____ Verify display works and no ALARMS are present

_____ If display does not work, turn off both circuit breakers immediately

_____ Follow instructions in Installation Manual Section: Start-Up Instructions to turn on the Seakeeper

_____ Verify seawater pump turns on while the Seakeeper is turned ON. The Seawater Pump operates
intermittently when cooling is needed.

_____ Verify no ALARMS are present

_____ Turn off the Seakeeper

_____ AC & DC power and seawater pump breakers may be turned off after the Seakeeper is turned off.

_____ Seakeeper 10 takes 4+ hours to coast down to 0 RPM from full speed.