6.1 Installation and Start Up Checklist Introduction

Reference Documents & Drawings:

The Installation and Start-Up Checklists in this section provide an overview of the primary steps covered in the installation manual and should be referenced throughout the installation process. Upon completing the Seakeeper 1 installation, the installer should commission each Seakeeper unit with the Seakeeper Commissioning Form (90437). The Commissioning Checklist Work Instruction (SWI-105) provides a checklist of items to inspect and verify during the commissioning process and supplements the Seakeeper Commissioning Form (90437).

All Seakeeper stabilizers should be commissioned to verify that installation specifications and requirements have been implemented properly. The commissioning process should include completing the Seakeeper Commissioning Form (90437), all the items in the Installation Checklist, and verifying that Seakeeper 1 operates without alarms or abnormal behavior.